Sunday, March 28, 2010

Mary Skinner apts. are Finished

If you don't receive pictures with this email they can be viewed at www.solarandrain.blogspot.com 

Here are the finish pictures for Mary Skinner apartments.  Everything got insulated and labeled.  EWEB came and inspected the system for completion and all city permits have passed inspection.  We are very happy with the way this project went from start to finnish.  Now that the systems have been leak tested and filled with the heat exchanger fluid they are producing preheated water temperatures up to 120 degrees.  Even in cloudy ol' Eugene!

Pacific Solar and Rain would like to give special thanks to:

St. Vincent depaul
HACSA
Sunearth Solar
Ferguson plumbing supply
Keller plumbing supply
Brigham Construction









EWEB

Monday, March 1, 2010

Started plumbing building 4 today.

Most of the potable water plumbing got finished in the utility room today, but we haven't received the balancing set yet. We should have them tomorrow, until then we'll be insulating more, wiring controllers and plumbing T&P relief valve.

The electrician will be there tomorrow to start wiring the water heaters for the switch over from old WH's to the new WH's

Today we started in building #4. We got the solar loop started and almost done, then started on the potable water plumbing. You can see the solar tree ( pump, flowmeter, fill set and expansion tank ) in the back ground. The water heater is on the left and the two 120 gallon solar tanks ( that are plumbed in parallel) are one the right. We got some insulating done too.

Tomorrow we will have all of the potable water loop done and insulated..